With the shorter Thanksgiving week, not much occurred other than the Strong-Wall installation, and inspections for rough framing, rough electrical, rough mechanical (i.e., HVAC), and rough plumbing — all which passed. The following week the solar PV inspection passed, and we got a new smart digital meter, so the panels now feed the grid (albeit more slowly with the clouds). In addition, insulation was installed, as was the remaining exterior lath.
Pink and fluffy!
A couple large stacks of drywall were also delivered. They haven’t been installed yet — perhaps next week? Fortunately, however, it is drywall made locally.
You may see more photographs at the gallery. There are two pages of albums for this project, so here’s a link to weeks 9 and 10.